We are facing a time crunch the DOE period for public comment will close of June 14, 2012.
The NYS PSC period for public comment will close on June 29, 2012.

The most concerning aspects of this project-
1- Rockland County seems not to know about this project.
2- Most of the studies were done in 2010
3- Most of the studies were done as a "Hudson River Installation"
4- Where are the studies that were done SPECIFICALLY for a land installation?

Attached is the DOE 2010 SCOPING document- with the project to be installed in the Hudson River from Canada to NYC.

Department of Energy – DOE, Presidential Permit

EIS-0447: Champlain Hudson Power Express Transmission Line Project, New York

 

Summary

This EIS evaluates the environmental impacts of a DOE proposal to grant a Presidential permit to Champlain Hudson Power Express, Inc., to construct, operate, maintain, and connect a new 1000-megawatt (MW) electric transmission system across the U.S.-Canada border in northeastern New York State. The proposed transmission line will run from the Canadian Province of Quebec to New York City.


Public Comment Opportunities


DOE is accepting public comments on the revised scope of the Champlain Hudson Project EIS until June 14, 2012. DOE will consider comments submitted after this date to the extent practicable. Written comments on the revised scope of the EIS may be mailed to: Brian Mills, Office of Electricity Delivery and Energy Reliability (OE–20), U.S. Department of Energy, 1000 Independence Avenue, SW, Washington, DC 20585; faxed to 202–586–8008; or emailed to Brian.Mills@hq.doe.gov.


Documents Available for Download


· APRIL 30, 2012
EIS-0447: Amended Notice of Intent to Prepare an Environmental Impact Statement
Champlain Hudson Power Express Transmission Line Project, New York
· MARCH 30, 2012

Information Notice -- Champlain Hudson Project, March 30, 2012
Champlain Hudson Project, March 30, 2012
· JUNE 18, 2010
EIS-0447: Notice of Intent to Prepare an Environmental Impact Statement and Conduct

Public Scoping Meetings
Champlain Hudson Power Express Transmission Line Project, New York

2- Article VII, Major Electric and Gas Transmission Facilities


Guide to Article VII and a Flowchart showing the progression of the applications


Website for - Article VII

Certified Article VII Cases -APPROVED

Filed Article VII Cases PENDING
08-T-0034 - Hudson Project 345 kV
08-T-1388 - LIPA - Riverhead to South Hampton 138kV
09-T-0049 - Upstate NY Power Corp., Galloo Island Project Transmission line 230kV
09-T-0870 - National Grid - Lockport to Mortimer 115 kV
10-T-0080 - National Grid - Spier Falls to Rotterdam 115 kV
10-T-0139 - Champlain Hudson Power Express 300kV
10-T-0154 - St Lawrence Gas
11-T-0068 - National Grid - Mohican to Battenkill 115kV

3- NYISO - Independent System Operator – (ISO)

This organization could be a great resource to Rockland County, we should belong to it.
The reliability of the transmission system in New York is the responsibility of the New York Independent System Operator (NYISO). An interconnection application has been filed with the NYISO in connection with the Project, and technical studies will continue to be performed in the months ahead.

4- Description of Proposal

The Champaign Hudson Power Express-

Donald Jessome
Chief Executive Officer
518-465-0710
600 Broadway
Albany, NY, 12207

5- Attached is the Party List for the CHPE Project-

The parties representing Rockland County

#4- Allen R. Beers #45- Linda Grant
Coordinator of Environmental Resources Senior Assistant County Attorney
beersA@co.rockland.ny.us grantl@co.rockland.ny.us

Ph- 845-364-2670 Ph- 845-638-5181

6- Main web site to CHPE


4a- Maps to project

7- April 12, 2012 -CHPE held a Public Comment session in Haverstraw NY at the Town Hall,

When I attended the April 12, 2012 meeting in Haverstraw there were about 5 people present. Including Supervisor Phillips. I pointed out to the Administrative Law Judge Michelle Phillips, that the public notice that is mandatory for this type of meeting was not very well done. I could not find a notice in any of the local papers for this meeting. I knew because I monitor the PSC main page

There are 2 Administrative Law Judges

1- Michelle Phillips

Ph-518-474-6517

2- Kevin Casutto

Ph-518-474-4529

NYS PSC web site Library for the CHPE Proposal

NYS PSC web site for Public Comment

8- CSX Right of Way through Rockland County

At this point in time I cannot find any information for this ROW

April 30,2012 –Federal Register- Notice of CHPE Route Change

9- The UNANSWERED questions



10- REPLACEMENT FOR INDIAN POINT

Several groups have already said that the see the CHPE Proposal as a way to shut down Indian Point. Id that is the case then the installation is much bigger than is being currently proposed.

My biggest fear is that if this line is approved, then a year from now, we are told that instead of 1,000 megawatts CHPE has been given permission to install 3,000 , 4,000, 5,000 megawatts and the Towns of Stony Point Haverstraw and Clarkstown become a highway for HIGH VOLTAGE DC CURRENT DEDICATED TO NYC. Once this transmission line is installed it sets a precedent of installation here in Rockland, and that is something I do not believe we can afford.

11- What CHPE does not do for Rockland County/NYS

This will be Stony Point's and Haverstraw's second go round with Blackstone- they are not good corporate neighbors as can be seen by June 2, 2012, article in the Rockland County Journal News, where GenOn is insisting on yet another tax reduction on property (Bow Line) they stripped and sold piecemeal.

12- Deregulation – does the CHPE Proposal meet and adhere to NYS Law?

The final point I would make is that there is a question of NYS Deregulation Law– does CHPE's application as a "Merchant" pipeline violate NYS Deregulation law? In its simplest definition "Merchant" means that the owner of the transmission line is also the owner of the electric generation, and that they are allowed to roll the costs of building the Generating Plants into the cost of the transmission line. Deregulation within NYS separated those two functions and created law to prevent NYS utilities from being both the owner of generation and the owner of the pipes and wires.

Blackstone Group owns both Transmission Developers, Inc.(they will build the infrastructure - transmission line to move the electric from Canada to NYC) and Champlain Hudson Power Express(the will purchase and or perhaps own -supply of electric

Who will regulate this transmission line that originates in Canada, NYS or Canada?

13- Concerned Residents of Hammond

14- Links to Newspaper Articles

Conservation Law Foundation

Posts Tagged 'Champlain Hudson Power Express' May 24, 2012 by Christophe Courchesne | Leave a Comment

LoHud-

Champlain Hudson Power Express faces resistance, exe sites jobs and cheaper electricity

Coming Wednesday on Editorial Spotlight: Energy line under Hudson, along CSX tracks
Green Law, PACE Law School

Rockland County Times

Champlain Hudson Power Express Project Will be Discussed June 26 in Stony Point Posted May 24th, 2012

Riverkeeper

Sierra Club- No to the Champlain Hudson Power Express

Lake Champlain Life, - what is the Champlain Hudson Power Express

...And these documents:

Blackstone owns Champlain Hudson Power Express

Party List for CHPE

NYS Article VII Guide

Federal Register - Notice of Route Change

Route through Rockland

CHPE Scoping Summary Report